Main Span
Photo not archived
West Pylon
8th cable pulled (see right side) Note also that the booms of the two platform crans has been dropped to the platform, I suppose in preparation for high winds from Charley
East Pylon
Extension to 8th anchor (see left side)
Photo not archived
Photo not archived
August 14, 2004 - After Hurricane Charley
Closing the West Approach Gap: Note the cap completion on the approach pier and a pair of hurricane cable anchors in the river (lower center)

Closing the East Approach Gap: Note the extension of the channel side of the platform (8th anchor) and forms in place for pouring the cap on the approach pier
Photo not archived