Closing the West Approach Gap: 9th cable bundle being pulled on the channel side
By my counting, this is > 50% complete on the channel side of the west tower..
Photo not archived
Closing the East Approach Gap: 8th cable bundle pulled, and more work on
the cap for the last approach pier. From the remaining holes in the pylons,
it appears that the platform is 50% complete - 8 (or 9) remaning cables
bundles to be pulled and anchored. (Click on the image and count the
holes above the last cable).
West Approach (Cap complete and porta-potty installed). Note the barge with
concrete rectangles. These are the roadbed segments that are lifted and
placed on the beams seen at the top right of the photo. See
(near the top for lifting and placing a section or
for positioning one of these concrete sections
Photo not archived
East Approach (Forms in place for pouring concrete cap, completing the pier = 2 columns + cap)