February 5, 2005: Bridging the Channel Gap
This week, the stay pipes and cables attached to the last pair of anchors (316) were erected
The next morning, Feb 6, 2005: The concrete floor panals have been placed and now the east deck is lower than the west deck.

From the old bridge where you can see my weekly photo spot - about 1 km next to the vertical loading machines

February 1, 2005: Starting the stay cable assembly

February 4, 2005: Finished stay cable assembly