Composing a another movement of the symphony of barges
July 4, 2004
Last week, I sort of stumbled upon the placing of steel beams on their support piers and I got to thinking about the logistics and orchestration of the fabrication, transport, delivery, positioning and final attachment of all the zillions of pieces bridge stuff. What does the staging of construction material delivery look like. So this week, I focused on the construction of the circular piers as well as the bridge platform and noticed the barges aligned and ready to deliver the next batch of stuff.
A line of barges with different construction materials - beams with attached cable anchors, cement trucks, circular forms and rebar. Note the two spuds to the left of the crane (click on the left image to see the full image) that anchor the crane to the river bottom. Much of the steel is fabricated by High Steel Structures.
Growing the west side piers
Growing east side piers - looking east and looking west
Anchors waiting by the Yorktown
A waiting cement mixer for filling the forms for the west approach pier
July 18, 2004 Continued movement of beams to the east and west piers
September 25, 2004 Two helper tug boats and helping men