Closing the Gap between the Approaches and the Pylons
February 12, 2005:
West Approach
East Approach
Freyssinet completes the last (416) stay cable
West Approach
East Approach
West Approach
East Approach
Note the cable bundle on the second of the triple anchors on the last edge girder.
West Approach
East Approach
Note the cable bundle on the first of the triple anchors on the last edge girder.
Not much changed on the west side during the
Christmas holidays that I can see. On the east side, though, the
14th cable bundle (the first anchor on the triple anchor edge girder) has
been built.
West Approach
East Approach
Note the cable bundle on the first of the triple anchors on the last edge girder.
West Approach
East Approach
December 18, 2004
West Approach
East Approach
December 12, 2004: Finishing the approach - deck cables
The east approach is now spliced to the east deck
and the 13th cable bundle was built
West Approach: The master strand for the 15th cable bundle has been pulled
The west triple anchor girder - a view of the master strand
The west approach expansion gap
East Approach: Note that the 13th cable has been built
Note below that the 15th cable was started
The finished splice between the east approach and the east deck
A view of the splice between the east approach and deck
December 5, 2004
Building the east approach 13th cable bundle -
cable rig is now in place and disassembly of the west approach crane.
The counterweights have been removed from the west platform now that it
is attached to the west approach. You can see the counterweights on the
east platform (channel side, left) which will be removed once the east
platform is attached to the east approach. In addition, the hurricane
cables have been removed from the west deck.
West Approach
Note the hurricane cables have been removed
East Approach
Note counterweights on the channel side
Linking the east approach with the east platform
East Approach:
Last night the edge girders were placed. Look closely
and you can see the misalignment between the platform and the approach.
During the next week the edge girder will be aligned for splicing. But
first, the cable must be built and partially tensioned (which will provide
for vertical alignment).
December 1, 2004
Building the 14th (2 more to go) cables on the
west end of the plagform (the first of the triple anchor girder).
West Approach
East Approach
West Approach
East Approach
West Approach: Note addition of 13th anchor girder and cable bundle on the channel side
East Approach
Linking the west approach with the west platform is complete. Now for the east approach.
West Approach
East Approach
West Approach
East Approach
A close view of splicing the platform edge girder with the approach edge girder. You can see the splice plate that will join the platform and approach edge girders pinned in place, but unbolted. There is less than 1 inch of vertical misalignment and about 1 - 2 inches of horizontal misalignment See west gap page
November 1, 2004: After erecting the 1st anchor beam linking the west approach with the west deck
David Wertz from the SC DOT has clued me in about the complexities of connecting the final anchor beams - joining first the west approach with the west deck and in about a month, the east approach with the east deck. (Check out Closing the West Gap) David said:
"Interestingly enough, neither one of the girders will actually be connected to the approach span until possibly next week. As you probably noticed, the west end of the girder is hanging a couple of feet lower than the approach girder. In order to get everything lined up right, the rest of the steel on this segment will have to be placed, the net traveler will have to be rolled onto this segment, the entire west tower deck will have to be "unjacked" back toward the approach, the next pair of cables will have to be installed and partially tensioned, additional tensioning will have to be done to the previous pair of cables, deck counterweights will have to be moved, and deck panels will have to be placed. Then and only then will all of the bolt holes be lined up perfectly to do the final bolt-up at the connection to the approach.""To add a little detail to the "unjacking" that was mentioned, last week, the entire 1/4 mile long west deck was jacked toward the channel about 3 1/2" using a few 200 ton hydraulic jacks to prepare for the placement of the last two edge girders. The deck will have to be slowly and partially released back to get the alignment just right for the final connection."
West Approach
East Approach
October 31, 2004:Before erecting the edge girder connecting the west approach with the west deck
October 22, 2004:
West approach: Completing 12th cable bundlesOctober 17, 2004:
West approach: Addition of the 12th anchorsWest approach looking west
West approach looking east
East approach looking west
East approach looking east
October 15, 2004:
West approach:October 9, 2004:
West approach: Completing the 11th cable bundle (approach side)October 2, 2004:
West approach: Building the 11th cable bundle (channel side) East approach: Completion of 10th cable bundle (approach side)Note the addition of the short beams on the cap (right bottom photo). The top photo was taken at 5pm Oct 02, the middle on at 8am Oct 03 and the bottom one at 5pm. Now the mystery is clear - they are joining the last two approach piers.
September 19, 2004: 10th anchor set added to west platform, hurricane cables completed (both platforms).
West approach East approach: Addition of the 2nd set of hurricane cablesCompletion of steel beams spanning the last two west approach piers.
Finishing the cap
September 24, 2004: 10th cable sets pulled.
West approach East approachSeptember 12, 2004: A foggy morning bike ride
West approach East approachAddition of the last three cable anchors on the approach pier.
Building the cap
West approach - About 4 hours later (7pm)
August 21, 2004
Closing the West Approach Gap: 9th cable bundle being pulled on the channel sideBy my counting, this is > 50% complete on the channel side of the west tower..
Closing the East Approach Gap: 8th cable bundle pulled, and more work on the cap for the last approach pier. From the remaining holes in the pylons, it appears that the platform is 50% complete - 8 (or 9) remaning cables bundles to be pulled and anchored. (Click on the image and count the holes above the last cable).
August 7, 2004 - A very warm light from the sun that is saying goodbye
Closing the West Approach Gap
Closing the East Approach Gap
July 31, 2004
Closing the West Approach Gap
Closing the East Approach Gap
July 17, 2004
Closing the west approach gap
Closing the east approach gap
July 4, 2004
June 27, 2004
West Approach
West Pier
East Pier