Closing the Gap between the Approaches and the Pylons

February 12, 2005:

West Approach

Photo not archived

East Approach

Photo not archived
West Approach:
East Approach:

Freyssinet completes the last (416) stay cable

Photo not archived
Photo not archived
January 22, 2005:

West Approach

Photo not archived

East Approach

Photo not archived
West Approach:Last of the triple anchor cables built - fini!
East Approach:
Photo not archived
Photo not archived
A view of the west approach pier - looking east
Photo not archived
A view of the west approach pier - looking west
Photo not archived
January 15, 2005:

West Approach

Photo not archived

East Approach

Photo not archived
West Approach:
East Approach:

Note the cable bundle on the second of the triple anchors on the last edge girder.

Photo not archived
Photo not archived
January 8, 2005:

West Approach

Photo not archived

East Approach

Photo not archived
West Approach:
East Approach:

Note the cable bundle on the first of the triple anchors on the last edge girder.

Photo not archived
Photo not archived
January 2, 2005:

Not much changed on the west side during the Christmas holidays that I can see. On the east side, though, the 14th cable bundle (the first anchor on the triple anchor edge girder) has been built.

West Approach

Photo not archived

East Approach

Photo not archived
West Approach:
East Approach:

Note the cable bundle on the first of the triple anchors on the last edge girder.

Photo not archived
Photo not archived
December 23, 2004

West Approach

Photo not archived

East Approach

Photo not archived
West Approach:
East Approach:
Photo not archived
Photo not archived

December 18, 2004

West Approach

Photo not archived

East Approach

Photo not archived
West Approach:
East Approach:
Photo not archived
Photo not archived
Photo not archived
Photo not archived

December 12, 2004: Finishing the approach - deck cables
The east approach is now spliced to the east deck and the 13th cable bundle was built

West Approach: The master strand for the 15th cable bundle has been pulled

Photo not archived

The west triple anchor girder - a view of the master strand

Photo not archived

The west approach expansion gap

Photo not archived

East Approach: Note that the 13th cable has been built

Photo not archived
West Approach:
Note below that the 15th cable was started
East Approach:
Photo not archived
Photo not archived
Photo not archived
Photo not archived
A view of the top of the west pylon
Photo not archived
A view of the top of the east pylon
Photo not archived

The finished splice between the east approach and the east deck

Photo not archived

A view of the splice between the east approach and deck

Photo not archived

December 5, 2004
Building the east approach 13th cable bundle - cable rig is now in place and disassembly of the west approach crane. The counterweights have been removed from the west platform now that it is attached to the west approach. You can see the counterweights on the east platform (channel side, left) which will be removed once the east platform is attached to the east approach. In addition, the hurricane cables have been removed from the west deck.

West Approach
Note the hurricane cables have been removed

Photo not archived

East Approach
Note counterweights on the channel side

Photo not archived
West Approach: It appears that the crane has been disassembled (tear down time?)
East Approach: The cable building rig has been moved into position adjacent to the 13th anchor (on the edge girder erected last week)
Photo not archived
Photo not archived
December 2, 2004 - Lots of action today
Linking the east approach with the east platform

East Approach:
Last night the edge girders were placed. Look closely and you can see the misalignment between the platform and the approach. During the next week the edge girder will be aligned for splicing. But first, the cable must be built and partially tensioned (which will provide for vertical alignment).

Photo not archived
Photo not archived

December 1, 2004
Building the 14th (2 more to go) cables on the west end of the plagform (the first of the triple anchor girder).

West Approach

Photo not archived

East Approach

Photo not archived
West Approach:
East Approach:
Photo not archived
Photo not archived
November 28, 2004

West Approach

Photo not archived

East Approach

Photo not archived
West Approach:
East Approach:
Photo not archived
Photo not archived
November 21, 2004

West Approach: Note addition of 13th anchor girder and cable bundle on the channel side

Photo not archived

East Approach

Photo not archived
West Approach:
East Approach:
Photo not archived
Photo not archived
November 14, 2004
Linking the west approach with the west platform is complete. Now for the east approach.

West Approach

Photo not archived

East Approach

Photo not archived
West Approach:
East Approach:
Photo not archived
Photo not archived
Photo not archived
Photo not archived
Nov 6, 2004: Continued work to connect the west approach with the west deck (see West Gap). There are two dimensions of adjustment required to close the gap between the approach and main bridge platform. The support cables can be tensioned to raise the bridge while hydraulic pumps can be used to laterally move the bridge platform. The slight bowing in the south (13th) cable sheath indicates that the they have not reached their final tension and are being slowly adjusted in order to achieve the correct alignment of the approach and platform edge girders. From this distant vantage point, the beams appear virtually aligned and perhaps the splice plates have been pinned into place with several drift pins? (click the close-up below left). It appears that the work platform has been positioned under the junction of the approach and platform beams.

West Approach

Photo not archived

East Approach

Photo not archived
West Approach: Note edge girder on the near side
East Approach:
Photo not archived
Photo not archived
Photo not archived
Photo not archived

A close view of splicing the platform edge girder with the approach edge girder. You can see the splice plate that will join the platform and approach edge girders pinned in place, but unbolted. There is less than 1 inch of vertical misalignment and about 1 - 2 inches of horizontal misalignment See west gap page

Photo not archived

November 1, 2004: After erecting the 1st anchor beam linking the west approach with the west deck

David Wertz from the SC DOT has clued me in about the complexities of connecting the final anchor beams - joining first the west approach with the west deck and in about a month, the east approach with the east deck. (Check out Closing the West Gap) David said:

"Interestingly enough, neither one of the girders will actually be connected to the approach span until possibly next week. As you probably noticed, the west end of the girder is hanging a couple of feet lower than the approach girder. In order to get everything lined up right, the rest of the steel on this segment will have to be placed, the net traveler will have to be rolled onto this segment, the entire west tower deck will have to be "unjacked" back toward the approach, the next pair of cables will have to be installed and partially tensioned, additional tensioning will have to be done to the previous pair of cables, deck counterweights will have to be moved, and deck panels will have to be placed. Then and only then will all of the bolt holes be lined up perfectly to do the final bolt-up at the connection to the approach."

"To add a little detail to the "unjacking" that was mentioned, last week, the entire 1/4 mile long west deck was jacked toward the channel about 3 1/2" using a few 200 ton hydraulic jacks to prepare for the placement of the last two edge girders. The deck will have to be slowly and partially released back to get the alignment just right for the final connection."

West Approach

Photo not archived

East Approach

Photo not archived
West Approach: Note edge girder on the far side
East Approach:
Photo not archived
Photo not archived

October 31, 2004:Before erecting the edge girder connecting the west approach with the west deck

West Approach:
East Approach:
Photo not archived
Photo not archived

October 22, 2004:

West approach: Completing 12th cable bundles
Photo not archived
East approach: Addition of the 12th anchors
Photo not archived
West Approach: Completed the 12th cable bundles
East Approach: Completed the installation of the east pier triple anchor beam
Photo not archived
Photo not archived

October 17, 2004:

West approach: Addition of the 12th anchors
Photo not archived
East approach
Photo not archived
West Approach: click image to view anchor beams
East Approach: Adding the last 3 anchors to the approach pier
Photo not archived

West approach looking west

Photo not archived

West approach looking east

Photo not archived
Photo not archived

East approach looking west

Photo not archived

East approach looking east

Photo not archived

October 15, 2004:

West approach:
Photo not archived
East approach
Photo not archived
West Approach: Only 3 weeks til the gap is closed
East Approach:
Photo not archived
Photo not archived

October 9, 2004:

West approach: Completing the 11th cable bundle (approach side)
Photo not archived
East approach
Photo not archived
West Approach: 11th cable bundle, 2 anchors to go
East Approach:
Photo not archived
Photo not archived

October 2, 2004:

West approach: Building the 11th cable bundle (channel side) East approach: Completion of 10th cable bundle (approach side)
Photo not archived
West Approach:
East Approach:

Note the addition of the short beams on the cap (right bottom photo). The top photo was taken at 5pm Oct 02, the middle on at 8am Oct 03 and the bottom one at 5pm. Now the mystery is clear - they are joining the last two approach piers.

Photo not archived
Photo not archived

Waiting -

Oct 2 5pm: the cap is bare

Photo not archived
Oct 3 8am: a beam appeared on the north side of the pier
Photo not archived

Oct 3 5pm: Now its clear - the beams for spanning the last two piers are being positioned

Photo not archived

September 19, 2004: 10th anchor set added to west platform, hurricane cables completed (both platforms).

West approach East approach: Addition of the 2nd set of hurricane cables
Photo not archived
West Approach:

Completion of steel beams spanning the last two west approach piers.

East Approach:

Finishing the cap

September 24, 2004: 10th cable sets pulled.

West approach East approach
Photo not archived
West Approach:
Photo not archived
East Approach: A finished cap
Photo not archived

September 12, 2004: A foggy morning bike ride

West approach East approach
Photo not archived
West Approach:

Addition of the last three cable anchors on the approach pier.

Photo not archived
East Approach:

Building the cap

Photo not archived
August 29, 2004 3 of the four deck cranes have their booms lowered, but all looks ok West approach: Note that poking up from the river under the end of the west (left) deck are the anchors for the next set of hurricane cables - just in time. East approach
Photo not archived

West approach - About 4 hours later (7pm)

Photo not archived
East approach
Photo not archived

August 21, 2004

Closing the West Approach Gap: 9th cable bundle being pulled on the channel sideBy my counting, this is > 50% complete on the channel side of the west tower..

Photo not archived

Closing the East Approach Gap: 8th cable bundle pulled, and more work on the cap for the last approach pier. From the remaining holes in the pylons, it appears that the platform is 50% complete - 8 (or 9) remaning cables bundles to be pulled and anchored. (Click on the image and count the holes above the last cable).

West Approach (Cap complete and porta-potty installed). Note the barge with concrete rectangles. These are the roadbed segments that are lifted and placed on the beams seen at the top right of the photo. See (near the top for lifting and placing a section or for positioning one of these concrete sections
Photo not archived
East Approach (Forms in place for pouring concrete cap, completing the pier = 2 columns + cap)
Photo not archived

August 7, 2004 - A very warm light from the sun that is saying goodbye

Closing the West Approach Gap

Closing the East Approach Gap

Photo not archived
West Approach
Photo not archived
East Approach
Photo not archived

July 31, 2004

Closing the West Approach Gap

Closing the East Approach Gap

Photo not archived
West Approach
East Approach

July 17, 2004

Closing the west approach gap

Closing the east approach gap

Photo not archived
West Approach
East Approach

July 4, 2004

West Approach
Photo not archived
East Approach
Photo not archived

June 27, 2004

West Approach

West Pier

East Pier

Photo not archived
Visit our Archives for links to all our web segments