The Tower Construction page, updated each week, is now getting out of hand. With a dial-up modem, my dad requires about 15 min to download the page. Now that the tower (pylon) construction is complete and work is focused on the deck and bridging the gaps to the east and west approaches and bridging the ship channel, I have decided to move the "ship channel gap photos" to this page and the approach gap photos here. The main page will simply continuing to show the entire bridge (from the Aquarium) on the Tower Construction page. This will remove a number of the photos and improve the download time. As usual, if you have some other suggestions, send me email
Closing the Center Gap
August 23, 2003
October 12, 2003
November 16, 2003
November 23, 2003
December 14, 2003: Starting the west platform
Jan 13, 2004: (early morning)
Jan 18, 2004: Starting the east platform
Jan 25, 2004 (cold, windy and dark)
Jan 31, 2004 (windy taken from the Aquarium)
Feb 15, 2004
Feb 15, 2004 5pm after the rain
Feb 22, 2004
Feb 28, 2004
March 7, 2004: 1st cable pulled
March 14, 2004
March 21, 2004
April 18, 2004
May 9, 2004: 2nd cable pulled
May 16, 2004
May 22, 2004: 3rd cable pulled
May 30, 2004
June 7, 2004 (4th cable pulled)
June 22, 2004 (5th cable pulled)
June 27, 2004
July 4, 2004 (hurricane cables attached - approach side of the west platform)
July 11, 2004 (hurricane cables attached - channel side of the west platform)
July 17, 2004 (6th cable pulled and hurricane cables attached to the east platform)
July 31, 2004 (7th cable pulled - channel side)
August 7, 2004 (8th anchor extension - channel side west; 7th cable cable pulled - channel side, east)
7am August 8, 2004
August 14, 2004
Note the cranes at the ends of the platform on each pylon have been dropped, I suppose to avoid problems with high winds from Charley
August 21, 2004
All four platform cranes are back with their booms extended
Eight cables (on the west) and 9 cables (on the east) remain to be pulled (on the channel side). There is one additional cable to be prepared on the approach sides.
August 29, 2004:about 3pm
After Gaston - sort of gloomy. You can see the new hurricane cable anchors just below the west end (left) of the deck
A few hours later (7pm)
September 1, 2004:
September 12, 2004:
You can see the recently added 2nd set of hurricane cables at the left edge of the west platform
September 19, 2004:
You can see the recently added 2nd set of hurricane cables at the right edge of the east platform
September 24, 2004:
10th cable sets pulled
October 2,2004:
Building the 11th cable bundles (west deck)
October 9,2004:
Completing the 11th cable bundles (west deck) - only 2 more anchors to add
November 14, 2004:
November 21, 2004:
Note addition of the 13th anchor and cable
on the west platform (channel side)
Note addition of the 13th anchor and cable on the west platform (compare with the Nov 14th photo)
November 28, 2004:
Note the shark-fin edge girders resting on the barge in the foreground
December 1, 2004
Building the 14th cable bundle(west backspan)
and erecting the 14th edge girder (west main span)

Where are the west-most hurricane cables? It seems that this set was temporary - to minimize lateral movement of the west deck until it could be connected to the west approach. Now that the approach has been attached to the back span, I suppose that these cables are no longer necessary. In addition, the counterweights are being removed since a balancing act is no longer required (thanks to David Wertz, SCDOT).
5pm: Erecting the 14th edge girder (if I counted correctly)

10 minutes later

A close look at the girder

I am often surprised by what is available to be seen by that I do not see. I was so focused on capturing the new cables and their curved stay-cable pipes that I completely missed the fact that the west-most hurricane cables are now absent. I only discovered this change when I was annotating this photo.
December 2, 2004: Erecting the floor beams for the 14th edge girders
Slowly slowly lifting the floor girder from the barge

And slowly slowly dropping the floor girder into place. Note the traffic cop under the right of the beam directing the crane operator

December 5, 2004: Bridging the Channel Gap
December 12, 2004: Bridging the Channel Gap

Extending the east platform (Adding the 13th segment)

Here are the cranes poised to build the next segment
West deck

East Deck

December 18, 2004: Bridging the Channel Gap


Avoiding traffic on the Pearman bridge has its advantages. Each Sunday morning, I start my bicycle trip across the bridge in order to avoid traffic and get a few close photos of what is happening. The timing often coincides with early sunrise and the views are simply spectacular.


December 23, 2004: Bridging the Channel Gap
January 8, 2005: Bridging the Channel Gap
Big progress this
week. On the west platform the LAST (16th) edge girders are in place
(if I counted correctly), while on the east platform, the cable bundles
have been built and floor girders erected and attached to the edge
girders that were in place last week.
Here are views of the "gap" from the old bridge - looking east
Looking west (click on the photo and look for the two anchored barges with the last two pairs of edge girders and associated floor girders)

January 2, 2005:Bridging the Channel Gap - note the addition of the 14th edge girders to the east platform

Look carefully and you can see the new edge girders projecting out from the east platform. Next the floor beams will appear but I did not see a barge with the floor girders.

January 15, 2005:Bridging the Channel Gap
January 22, 2005:Bridging the Channel Gap
Note the 15th cables completed on the east side
January 23, 2005 morning
Almost complete - 1 more anchor edge girder and then the 10 foot center edge girder to join the east and west platforms

A view of the gap from the old bridge. At -1 C, there is little haze and the Charleston harbor looks very picturesque this morning.

January 30, 2005:Bridging the Channel Gap
Note the addition of the last pair of shark fin edge girders
4pm
In addition to the edge girders, it appears that 2 floor girders have also been placed
January 28, 2005: Erecting the last shark fin edge girder
February 5, 2005: Bridging the Channel Gap
This week, the stay pipes and cables attached to the last pair of anchors (316) were erected
The next morning, Feb 6, 2005: The concrete floor panals have been placed and now the east deck is lower than the west deck.

From the old bridge where you can see my weekly photo spot - about 1 km next to the vertical loading machines

February 1, 2005: Starting the stay cable assembly

February 4, 2005: Finished stay cable assembly
February 12, 2005:Bridging the Channel Gap
This week, the stay pipes and cables attached to the last pair of anchors (416) were erected
Now a bridge bridges the gap between the east and west decks.

A view of the gap from the top of the east pylon

From the old bridge

February 20, 2005:Bridging the Channel Gap

This week, (actually Friday night and Saturday morning) the north and south center edge girders were erected. With your best imagination, you can see the splice plate and vertical stiffener

To help your imagination, here are the spliced girders at the Navy Yard (Jan 26)

February 27, 2005:Bridging the Channel Gap and a view from the Pearman bridge


To help your imagination, here is a view of the last gap as seen from the Pearman bridge

March 6, 2005:
The Channel Gap < 6 inches and a view from the Pearman bridge

To help your imagination, here is a view of the last gap as seen from the Pearman bridge. Note the fairing installed along the edge girders on the west side. Soon similar wind breakers will be installed on the east side. You can see pairs of attachment points on the vertical stiffeners on the east edge girders.

March 13, 2005:Bridging the Channel Gap and a view from the Pearman bridge

1pm
March 15, 2005: The west tower crane grows down a little more

March 18, 2005: Look dad, the west crane's boom disappeared

1pm
From the Pearman Bridge - a nice view of Charleston under the center edge girder of the bridge
March 19, 2005:Bridging the Channel Gap
Look dad at the small crane to the left of the west pylon.
The west crane's boom disappeared and the crane continues to grow down

March 26, 2005: Bridging the Channel Gap
Look dad, the west tower crane disappeared
April 2, 2005:Bridging the Channel Gap
April 6, 2005:The East Tower Crane is growing down
If you look carefully (click on the image) you can see 1 tower segment resting
on the main span deck and 2 tower segments resting on a barge at the foot of
the tower. In addition, the upper strut assembly, connecting the tower
crane with the concrete pylon, has been removed.

April 8, 2005:Bridging the Channel Gap
The East Tower Crane is growing down. There were 4 horizontal supports connecting the tower crane with the pylon (look at April 2 photos). Two days ago (April 6) there were only 3 horizontal supports. Now there are only two.
April 9, 2005:Bridging the Channel Gap
The East Tower Crane continues to grow down. Monday, I suspect the boom will disappear
April 14, 2005: Bridging the Channel Gap
The East Tower Crane is gone - except a segment of the jib, sleeping on the deck
April 15, 2005:Bridging the Channel Gap
Gone is the east
crane, the barge and everything
April 16, 2005:Bridging the Channel Gap
Gone is the east
crane, the barge and everything
April 23, 2005:Bridging the Channel Gap