East Bay Ramp
January 8, 2005
My first views of line 14 (East Bay on ramp)
January 15, 2005
Extending the edge girders
January 16, 2005
Preparing the pier cap and pouring concrete at the East Bay entrance
January 19, 2005
Adding center girders
January 20, 2005
Girders on the move - by truck that is
January 22, 2005
Cross bracing and a view from above
January 25, 2005
Two spans to go
January 28, 2005
Preparing the next set of girders
February 4, 2005
No gap between Line 14 and the Ravenel approach
February 5, 2005
Kissing cranes at the Ravenel junction
February 6, 2005
Last edge girder placed
February 12, 2005
Bidwell at work near East Bay - making roadway
February 20, 2005
Happy workers and placing the underside forms
February 27, 2005
Grace crossbraces removed
March 5, 2005
Building the bicycle/jogging path forms
March 13, 2005
The Bidwell paving machine - at work
March 19, 2005
Paving continues - and a view from the Pearman
March 26, 2005
Building the span under the Grace truss
April 2, 2005
Building the expansion joint at the Ravenel junction
April 11, 2005
Building the expansion joint
April 16, 2005
The bicycle detour around the Grace supports
April 23, 2005
Bicycle and jogging lane virtually complete
April 30, 2005
The last pour at the expansion joint
May 8, 2005
Building the entrance ramp from East Bay and the expansion joint
May 14, 2005
Painting and the expansion joint
May 27, 2005
Painting the lane boundaries
June 4, 2005
Pouring the bicycle / jogging East Bay entrance
June 11, 2005
East Bay on-ramp completed